Thursday, October 30, 2008


Thursday, October 30, 2008: Today the wind was calm enough for the crane to come back, and set the roof trusses over the upstairs.

Wednesday, October 29, 2008



Monday, October 27th,2008: Crane at work site today to set roof trusses. Was able to set the 1st floor roof trusses over the garage and master bedroom, but too windy to set the trusses over the upstairs. It is cold and windy on the hill!

October 28th and 29th: Still working on the garage and master bedroom roof. Still very windy and cold. Snow flurries on Tuesday.

Wednesday,October 29th: Electric company connected the electric today! Builders are now able to use electric, instead of running a generator.

Wednesday, October 22, 2008

Started framing Garage today


Wednesday, October 22, 2008: Today the framing of the garage walls began.

Tuesday, October 21, 2008

More upstairs framing


October 21, 2008: Upstairs framing continues with framing the outside walls in the back of the house, and sectioning off the different rooms. Oh, what a windy day to be working on the upstairs of a house on a hill!

Monday, October 20, 2008

Upstairs framing continues


October 20th: The upstairs sub flooring is in place, and framing of the walls started.

Saturday, October 18, 2008

Framing moves upstairs



Friday, October 17, 2008: The concrete Garage floor was poured in the AM, then the upstairs (floor)framing began. By the end of the day a majority of the upstairs sub flooring was in place.

Thursday, October 16, 2008

Framing progress



The house is taking shape, inside and out. Each room on the first floor is now sectioned off with 2x4 framing. I can now walk about, getting a feel for the size and flow of the rooms.

Tuesday, October 14, 2008

Framing continues



October 14,2008: Wow! What a difference a few days of framing can make.The inside of the first floor is taking shape.

Sunday, October 12, 2008

First floor framing begins



Friday, October 10,2008: The sub flooring is completed, and framing on the first floor begins.

Friday, October 10, 2008

Sub flooring is the next step


October 9-10,2008: On top of the floor trusses,the tongue and groove sub flooring is secured into place. I can now walk on my first floor!

House building continues with floors


October 6, 2008: After a brief delay, the floor trusses finally arrive. Within 3 days they are secured in place.