Tuesday, December 30, 2008
House building project continues
I haven't posted in a while, but there has been steady progress on the house.Christmas break, this past Thursday and Friday, were the only days without activity. The brick layers were able to lay brick December 18th and 19th,then the weather turned cold, and all brick work came to a halt. Monday, December 29th, a nice sunny day, brick work resumed. The electricians have been making steady progress in spite of the cold weather. The builders have been working on trim under the roof, and hardi plank siding on the bay window area. Today, the brick layers and electricians were working on site. Another nice sunny day.
Wednesday, December 17, 2008
Steady progress
I haven't posted in awhile, but work on the house has steadily continued. Brick work has been on and off, depending on the weather. They even worked this past Saturday! They have finished the back of the house.And now working on the front part of the house. Almost done! On Monday the electricians started their work. Monday, the tub in the master bath was delivered, and today framed around. Today, the builders started putting hardi-plank siding on. (It will go on odd areas of the house, instead of brick).
Wednesday, December 10, 2008
Monday, Dec.8th: In spite of the freezing cold, builders worked at putting soffit trim in place, and placing durock cement board in the bathrooms and laundry room. No brick work today! Tuesday, Dec. 9th: Brick work resumed. Laying brick on the back side of garage, and some on east side of house. Builders finished putting down durock cement board on the upstairs bathroom floor. Also, still working on soffit trim.
Friday, December 5, 2008
Slow and steady progress
Friday, December 5,2008: No brick work for past 2 days due to cold weather. Builder and crew worked on soffit trim. (the trim under the roof). Applying it is a slow and tedious process. The plumbers have also made steady progress these past 2 days. Today, the builders started putting down durock cement board in the bathrooms. I met with a flooring rep. on site today. He took some measurements,which will help me in making choices. A little early for floors, but I would rather not have last minute decision making. However, it will be mostly hardwood.
Wednesday, December 3, 2008
Busy day at work site
Wednesday, December 3,2008: Another busy day with lots of activity at the building site. Brick work continued on the east side of the house. Builders worked on basic framing of the wrap around porch, and soffit trim (under roof) on back of house, where the brick work is finished. Work with plumbing continued today, also.
Tuesday, December 2, 2008
After Thanksgiving break
Monday, December 1,2008: After Thanksgiving break, work on the house resumed today. The central vac.system(minus unit) was put in place today. Brick work resumed at the back of the house. Tuesday, December 2,2008: Today, lots of action. The plumbers started their work; heat and air work continued with putting in the upstairs unit; builders working with the bay window,and sitting area roofs; and brick work continued, moving around to the east side of the house.
Thursday, November 27, 2008
Brick Work Continues
The Stove
Up and Down Staircases
Monday, November 24,2008: Work began on the staircases.By Tuesday, the upstairs, and downstairs staircases were in place. Yes, the upstairs staircase is steeper then average. Which is OK with me, as our master bedroom is on the main floor, and I do not need to use this staircase every day. This way it will allow for more upstairs floor space. I refer to it as my Cardiovascular workout.
Thursday, November 20, 2008
Brick work progress
Wednesday, November 19, 2008
Heat and Air duct work begins
Tuesday, November 18, 20008: Today, the installation of the duct work began for heat and air. Openings cut here and there for the vents. They had met with us on site Monday, Nov. 10 to determine where the vents would go. What a cold day to be working with metal! Cold and windy with snow flurries on the hill.
Wednesday: Duct work continues. No brick work so far this week due to 30 some degree weather.
Friday, November 14, 2008
Brick work begins, doors installed
Wednesday, November 12,2008: Today, builder & crew started installing doors. Also, Masonry company started laying brick on back side of house. The brick is an Old Virginia 'Montpelier' brick. Brick work came to a halt at 3PM due to rain.
Thursday, November 13: Rain today. No brick work. Builder & crew worked on inside doors & such.
Friday, November 14: Today, brick work resumed. Finished the wall on the North side of the master bedroom. Work on doors continued.
Thursday, November 6, 2008
Windows installed
Tuesday, November 4th, Late afternoon: Pump to well installed. Muddy water at this time.
Wednesday, November 5th: After running the well pump for about 4 to 5 hours, the water is now clear. We are hopeful that our well will be OK.
--- Builder and crew started putting in windows today at the back of the house.
Thursday, November 6th: All the windows, except for 2, are now installed. Wow! That went fast.
Tuesday, November 4, 2008
Framing of roof
Thursday, October 30, 2008
Wednesday, October 29, 2008
Monday, October 27th,2008: Crane at work site today to set roof trusses. Was able to set the 1st floor roof trusses over the garage and master bedroom, but too windy to set the trusses over the upstairs. It is cold and windy on the hill!
October 28th and 29th: Still working on the garage and master bedroom roof. Still very windy and cold. Snow flurries on Tuesday.
Wednesday,October 29th: Electric company connected the electric today! Builders are now able to use electric, instead of running a generator.
Wednesday, October 22, 2008
Tuesday, October 21, 2008
More upstairs framing
Monday, October 20, 2008
Saturday, October 18, 2008
Framing moves upstairs
Thursday, October 16, 2008
Framing progress
Tuesday, October 14, 2008
Framing continues
Sunday, October 12, 2008
Friday, October 10, 2008
Sub flooring is the next step
House building continues with floors
Thursday, September 25, 2008
Basement framing continues
Sunday, September 21, 2008
Framing begins in the basement
Saturday, September 20, 2008
basement floor