Thursday, October 30, 2008


Thursday, October 30, 2008: Today the wind was calm enough for the crane to come back, and set the roof trusses over the upstairs.

Wednesday, October 29, 2008



Monday, October 27th,2008: Crane at work site today to set roof trusses. Was able to set the 1st floor roof trusses over the garage and master bedroom, but too windy to set the trusses over the upstairs. It is cold and windy on the hill!

October 28th and 29th: Still working on the garage and master bedroom roof. Still very windy and cold. Snow flurries on Tuesday.

Wednesday,October 29th: Electric company connected the electric today! Builders are now able to use electric, instead of running a generator.

Wednesday, October 22, 2008

Started framing Garage today


Wednesday, October 22, 2008: Today the framing of the garage walls began.

Tuesday, October 21, 2008

More upstairs framing


October 21, 2008: Upstairs framing continues with framing the outside walls in the back of the house, and sectioning off the different rooms. Oh, what a windy day to be working on the upstairs of a house on a hill!