Thursday, November 27, 2008

Brick Work Continues


Monday, November 24 through Wednesday, November 26, 2008: The brick work continues at the back of the house.

The Stove


This is D's five hundred,seventy pound toy. With the help of 4 other guys, he was able to place it in his basement cave on Monday November 24.

Up and Down Staircases



Monday, November 24,2008: Work began on the staircases.By Tuesday, the upstairs, and downstairs staircases were in place. Yes, the upstairs staircase is steeper then average. Which is OK with me, as our master bedroom is on the main floor, and I do not need to use this staircase every day. This way it will allow for more upstairs floor space. I refer to it as my Cardiovascular workout.

Thursday, November 20, 2008

Brick work progress


Thursday, November 20,2008: Today, the masonry crew was able to lay brick on the west side wall of the master bedroom. They stopped work at 1:30 pm due to expected temperature drop into the teens tonight. No other work at building site today.