Thursday, September 25, 2008

Basement framing continues


September 24, basement framing continues, dividing the basement into what will be finished and unfinished sections.

Sunday, September 21, 2008

Framing begins in the basement


September 19th: Framing in the basement began. Framing with 2x6's for exterior walls, & 2x4's for interior walls.

Saturday, September 20, 2008

basement floor


September 15: After a plastic moisture barrier is put down,concrete basement floor is poured. September 18th a sealant is put on the basement floor.

August & September: house construction continues

The basement walls are waterpoofed.


Basement walls in August
Getting ready for basement walls in August


Fadley Road Living

It all began on July 22nd after months of planning, approvals, and obtaining a building permit.